Engineering Change Orders (ECOs) — raise and manage controlled changes to products and BOMs. Covers the ECO list and review filter chip, raising a new ECO (title, product, change type, apply-on, target version, effective date, priority, reason, description), the full ECO record with 7-col details grid and version change, the Change Impact panel (where used, open sales/works/purchase orders), the approval sign-off and Apply (release) flow, all six change types (Correction, Improvement, Cost reduction, Customer request, Supplier change, Other), and the four-stage lifecycle (Draft → In review → Approved → Applied).

1 min read Engineering Manager, Quality Manager Updated August 2026

Section 01

What is an Engineering Change Order?

2 minutes

An Engineering Change Order (ECO) in Brytebuild is the formal mechanism for making a controlled change to a product record — its specification, drawing reference, materials, or Bill of Materials. Every ECO is traceable: it records what is changing, why, who approved it, and applies the change by incrementing the product version number.

  • Each ECO targets a specific product and specifies a Target Version — the version the product will reach when the ECO is applied
  • Changes can apply to the Product only (the product record) or Product + BOM (the product record and its bill of materials)
  • The ECO lifecycle is Draft → In review → Approved → Applied
  • An ECO must be submitted for review, then approved by a sign-off — it cannot be applied (versioned) without approval
  • Applying an approved ECO increments the product version and locks the ECO record
  • The Change Impact panel shows everything affected — assemblies the product rolls up into, open sales orders, works orders and purchase orders
Draft first, submit after review

Every ECO starts as a Draft. Use the draft phase to define the change clearly before submitting for approval. Once submitted it moves to In review and the reviewer signs off before you can apply it.

Section 02

The ECO list

1 minute

Navigate to Quality → Engineering Changes to view all ECOs. The 🏷 N in review chip shows how many ECOs are currently awaiting sign-off. Each row shows the ECO number, title, affected product, change type, current status and a View action.

Navigate toQualityEngineering Changes
🏷 2 in review
PrintDownload ExcelSearch records…
NumberTitleProductTypeStatusActions
ECO-2026-0003Add corrosion-resistant coating to bracket surface finishMTB-0062ImprovementIn reviewView
ECO-2026-0002Correct M8 bolt hole tolerance on Frame A mounting plateMTB-0062CorrectionIn reviewView
ECO-2026-0001Substitute SB-0404 bracket component — Steelco supply riskSB-0404Supplier changeAppliedView
Show 10 ▾ · Showing 1–3 of 3
«
1
»
Column What it shows
NumberAuto-assigned ECO reference — e.g. ECO-2026-0003. Immutable once raised.
TitleShort description of the change — e.g. Correct M8 bolt hole tolerance on Frame A mounting plate.
ProductThe product being changed — e.g. MTB-0062 (M8 Mounting Bracket — Frame A).
TypeThe change classification — Correction, Improvement, Cost reduction, Customer request, Supplier change, or Other.
StatusDraft (grey), In review (amber), Approved (blue), or Applied (green). Applied ECOs are locked.

Section 03

Raising a new ECO

2 minutes

Click + New ECO (top-right) to open the raise form. Fill in the title, select the product being changed, choose the change type, apply-on scope, target version, effective date and priority. Add a reason and description, then click Raise ECO — the ECO is created at Draft status.

Navigate toQualityEngineering Changes+ New ECO

New Engineering Change

Raise a draft ECO — submit for approval after reviewing

The ECO is created as a draft. Once you've defined the change, submit it for approval. Applying an approved ECO versions the product up to the target version.
Correct M8 bolt hole tolerance on Frame A mounting plate
MTB-0062
Correction
Product + BOM
2.0

The new version this change releases

As soon as applied
High
Goods-in inspection audit (AUD-2026-0001) identified dimensional tolerance failures for M8 Hex Bolts — Grade 8.8 batch PO-2026-0033 from Steelco Fasteners Ltd. NCR-2026-0008 raised. Root cause: incorrect tolerance specification on product drawing — current ±0.15mm should be ±0.08mm.
Update M8 Mounting Bracket — Frame A (#MTB-0062) product specification: revise bolt hole dimensional tolerance from ±0.15mm to ±0.08mm across all 4 mounting positions. Update BOM to add mandatory CMM-01 verification step at goods-in. Target version 2.00.
Field Required What to enter
TitleRequiredA short, specific description — e.g. Correct M8 bolt hole tolerance on Frame A mounting plate.
ProductRequiredSelect the product being changed — e.g. MTB-0062 M8 Mounting Bracket — Frame A.
Change TypeOptionalCorrection, Improvement, Cost reduction, Customer request, Supplier change, or Other. Defaults to Correction.
Apply OnOptionalProduct only — updates the product record. Product + BOM — updates the product and its bill of materials.
Target VersionRequiredThe version number the product will reach when the ECO is applied — e.g. 2.0. Must be greater than the current version.
EffectiveOptionalAs soon as applied — the change takes effect immediately on applying. On a set date — the change is scheduled for a specific future date.
PriorityOptionalLow, Normal, High, or Urgent. Defaults to Normal. Used to prioritise the approval queue.
ReasonOptionalWhy this change is needed — the root cause, NCR reference, customer request, or business rationale.
DescriptionOptionalWhat is changing — the specific product fields, BOM lines, tolerances, materials or documents being updated.

Section 04

The ECO record

2 minutes

Click View on any ECO to open its record. The record shows three sections: ECO Details (full change specification), Change Impact (everything affected), and Approval (sign-off and apply controls). The header shows the current lifecycle position.

ECO Details

Engineering Change Order — controlled change to a product (and optionally) its BOM

# Number

ECO-2026-0002

✏ Title

Correct M8 bolt hole tolerance on Frame A mounting plate

⬡ Product

MTB-0062

⊙ Type

Correction

⊙ Apply On

Product + BOM

⊙ Priority

High

⊙ Current Version

1.00

→ Version Change

1.00 2.00

📅 Effective

As soon as applied

⊙ Status

In review

Description

Update M8 Mounting Bracket — Frame A (#MTB-0062) product specification: revise bolt hole dimensional tolerance from ±0.15mm to ±0.08mm across all 4 mounting positions. Update BOM to add mandatory CMM-01 verification step at goods-in. Target version 2.00.

Reason

Goods-in inspection audit (AUD-2026-0001) identified dimensional tolerance failures for M8 Hex Bolts — Grade 8.8 batch PO-2026-0033 from Steelco Fasteners Ltd. NCR-2026-0008 raised. Root cause: incorrect tolerance specification on product drawing — ±0.15mm should be ±0.08mm.

Field What it shows
NumberAuto-assigned — e.g. ECO-2026-0002. Immutable.
TitleShort description of the change as entered when raising.
ProductThe product being changed — e.g. MTB-0062.
TypeThe change classification — see Section 07 for definitions.
Apply OnProduct only (product record only) or Product + BOM (product record + bill of materials).
PriorityLow / Normal / High / Urgent — for approval queue prioritisation.
Current VersionThe product's version before this ECO is applied.
Version ChangeThe before → after version — e.g. 1.00 → 2.00.
EffectiveAs soon as applied, or On a set date.
StatusCurrent lifecycle position — Draft, In review, Approved, or Applied.
DescriptionWhat is changing — the specific product fields, BOM lines or tolerances.
ReasonWhy the change is needed — root cause, NCR reference, or business rationale.

Section 05

Change impact

2 minutes

The Change Impact panel shows everything in Brytebuild that will be affected by this ECO. This gives approvers full visibility before sign-off — they can see which assemblies the product rolls up into and which open orders are currently using the product.

Change Impact

Everything affected by changing MTB-0062 — assemblies it rolls up into, open orders that use it

Where Used (1)

Assemblies

Frame Assembly FA-001 · uses as component

Open Orders Affected

Sales orders (2)

SO-2026-0043 · pendingSO-2026-0041 · pending

Works orders (3)

WO-2026-0018 · not startedWO-2026-0017 · in progressWO-2026-0016 · not started

Purchase orders (2)

PO-2026-0033 · ongoingPO-2026-0011 · ongoing
Impact area What it shows
Where UsedAssemblies and higher-level products that include this product as a component — i.e. the BOM roll-up. Blank if the product is not used in any assembly.
Sales ordersOpen sales orders that include this product — changing the product specification may affect pending deliveries.
Works ordersOpen production works orders for this product — in-progress orders may need to be halted or reworked before applying the ECO.
Purchase ordersOpen purchase orders for this product or its BOM components from affected suppliers (e.g. Steelco Fasteners Ltd, PO-2026-0033).
Review open orders before approving

If in-progress works orders exist when an ECO is applied, those orders may produce parts to the old specification. Co-ordinate with production before applying high-priority ECOs to decide whether to pause open works orders.

Section 06

Approval & applying an ECO

2 minutes

The Approval section at the bottom of the ECO record controls the sign-off and release flow. An ECO must move through review and approval before it can be applied (released). Applying the ECO versions the product up to the target version and locks the record.

Approval

Awaiting sign-off — once approved this ECO can be applied to version the product up

This engineering change is in review. Once the approver signs off, click Apply (release) to version the product up and lock the record.
Awaiting approval

Once the approver signs off, the Apply button becomes available:

Approval

Approved — ready to apply and version the product up

This ECO has been approved. Click Apply (release) to version MTB-0062 from 1.00 to 2.00 and lock the record. This action cannot be undone.
Apply (release)
Control Available when What it does
Go BackAlwaysReturns to the ECO list without changes.
DeleteDraft onlyPermanently removes the ECO. Not available once submitted.
Edit ECODraft onlyOpens the edit form — same as Raise ECO but pre-filled. Not available once submitted for review.
Submit for reviewDraft onlyMoves the ECO to In review status and triggers the approval workflow.
Awaiting approvalIn reviewRead-only indicator — shows the ECO is pending sign-off from the approver.
Apply (release)Approved onlyVersions the product up to the target version, locks the ECO record, and marks it Applied.
Apply is irreversible

Once Apply (release) is clicked the product version is incremented, the ECO is locked and cannot be edited or deleted. If an ECO was applied in error, raise a new ECO to revert or correct the product.

Section 07

Change types

1 minute

Every ECO is classified by change type. The type is for reporting and filtering — it does not affect the workflow. Choose the type that best describes the motivation for the change:

Correction

Fixes an error in the product specification or BOM — e.g. correcting a tolerance, drawing reference, or incorrect material. Typically linked to an NCR or audit finding.

Improvement

Enhances the product beyond its current specification — e.g. adding a corrosion-resistant coating, improving a manufacturing step, or upgrading a material grade.

Cost reduction

Changes that reduce manufacturing or material cost without compromising performance — e.g. substituting an equivalent lower-cost component or simplifying a BOM line.

Customer request

A change requested by a customer — e.g. a revised finish, modified dimension, or new packaging requirement specified in a sales order or customer contract.

Supplier change

A change driven by a supplier substitution or supply chain event — e.g. replacing Steelco Fasteners Ltd SB-0404 with an alternative supplier due to single-source risk or discontinuation.

Other

Any change that doesn't fit the above categories — e.g. regulatory compliance updates, label changes, or documentation-only corrections.

Section 08

ECO lifecycle

1 minute

Every ECO moves through a fixed four-stage lifecycle:

Status What's happening How to advance
DraftECO raised and being defined. Fully editable. Not yet visible to approvers.Click Submit for review once the change is fully defined.
In reviewECO submitted to the approver. Change Impact visible. Not editable.Approver signs off — moves to Approved.
ApprovedECO approved. Ready to be applied. Awaiting release.Click Apply (release) to version the product and lock the record.
AppliedProduct versioned up. ECO locked and read-only. Change is live.No further action. Record retained as evidence.