Fundamentals Beginner

Lead times — why the MRP tells you to order today

Where lead time is stored, how the order-by date is worked out, and the two settings that quietly wreck your dates.

4 min read All roles Updated August 2026

If the MRP keeps telling you to order things today, or hands you dates that are already past, it is almost always one missing number. This explains exactly how the order-by date is worked out, so you can see which one.

Part 01

A worked example

2 minutes

Acme orders 40 mounting brackets for 17 March. Each bracket needs one steel blank. You have 12 blanks free and none on order. Your supplier link for that blank says 14 days lead time and a minimum order of 50.

The run works outResultHow
What is needed40One blank per bracket, from the bill of materials.
What is short2840 needed, 12 free, nothing on order.
What to order50The shortfall is 28, but the supplier will not sell fewer than 50, so it is rounded up.
When to order by3 March17 March minus 14 days lead time.
Order by3 MarArrives17 MarNeeded17 Mar14 days supplier lead timeorder-by = needed date − lead time

So the run recommends buying 50 blanks, ordered by 3 March. Nothing is ordered until someone converts that recommendation into a purchase order — the date is telling you when the decision has to be made, not making it for you.

Part 02

Where lead time actually lives

1 minute

Lead time is not a property of the part. It sits on the link between a product and a supplier, alongside their minimum order quantity and price — because the same blank from a different supplier is a different wait.

This is why it is worth linking suppliers properly

A product with no supplier linked has no lead time, no minimum order and no price for the run to use. Linking the supplier is what turns a shortage list into a purchasing plan with dates on it.

Part 03

Three things that quietly wreck your dates

2 minutes

What you seeWhat is actually wrong
It says order by the date I need itNo lead time on the supplier link, so it is treated as zero days. The maths still runs — it just assumes delivery is instant, so you will always be late.
It wants more than I needThe supplier's minimum order quantity is higher than the shortfall, so the quantity is rounded up to it. Correct, but worth knowing before you question the number.
It says order within a week, with no reasonNothing gave that shortfall a deadline — no sales order date driving it — so a default of a week from today is used. That is a placeholder, not a calculation.
A missing lead time never shows up as an error

Zero is a perfectly valid number to subtract, so the run completes and looks normal. The only symptom is order-by dates that match the needed date exactly. If you see that across several parts, the supplier links are the place to look.

Part 04

Setting numbers that hold up

2 minutes

  • Use the wait you actually get, not the one you were quoted. If a supplier promises 10 days and delivers in 15, the honest number is 15. The MRP is not negotiating with them.
  • Include your own handling. If goods sit two days before anyone books them in, that is part of the wait as far as the shop floor is concerned.
  • Do not pad every part "to be safe". Padding buys stock you did not need and hides the suppliers that are genuinely slow. Fix the number on the part that was late instead.
  • Revisit after anything unusual. Lead times move. A number set once at rollout and never touched is the most common reason a run stops being trusted.
Where to start

You do not need every supplier link perfect. Set real lead times on the ten parts that stop a job when they are missing, and the run becomes useful immediately. The long tail can wait.